Deputy General Manager ( Project Manager ) in M/s. Punj Lloyd Limited, New Delhi.

Widening to 4/6 lanes and strengthening of existing 2-lane Carriageway from Km. 164.50 to Km.200.00 in Vijayawada - Vishakhapatnam Section of NH-5 (Gowthami Bridge to Divancheruvu ) NHAI Contract Package AP-17, near Rajahmundry Andhra Pradesh<

Project cost Rs. 81.35 crores.
Consultants : M/s. SNC-Lavalin International Inc. - Aarvee
Associates JV.
All the Project related activities were being executed with full momentum. Work done till Jan 25th 2003 was approximately Rs.28.63 Crores. The work was taken up in a length of 31 Kms. Items like Utility shifting, Clearing & Grubbing, Embankment, Sub-Grade, CD works, GSB, WMM , Prime Sealing , DBM , Kerb Laying etc. were being carried out as per MOST specifications. Preparation of Design Mix for BC was being carried out.
The Details of works executed are as under (NCW & ECW both Included):
Embankment : 5,74,210 cum, Linear 33.20 kms
Subgrade : 2,21,040 cum, Linear 31.46 kms.
GSB : 86,280 cum, Linear 29.21 kms.
WMM : 55,322 cum Linear 27.99 kms
DBM : 28,455 cum Linear 22.90 kms
Kerb : Linear 21.22 kms.
The stipulated date of completion of the project was December 2003. My appointment was on contract basis for 1 year, which was extended for another year up to December 2003..